The European Railway System ERTMS in Poland includes 15 000 km of railway lines. The main objective of this project was to perform the radio planning for GSM-R system of almost 7 500 railway lines, divided into 2 stages according to schedule of the Operational Programme Infrastructure and Environment No. 7.1-36 and 7.1-37.
. Radio planning
. Environmental analysis (human hazard, Natura 2000)
. Technical analysis
. Traffic analysis
. Frequency planning (including cross-border coordination – HCM)
. Interference analysis
. Optimization
. Report
This project was performed using Prospective planning and Route planning functions included in ICS designer as well as our new Frequency assignment engine.
More information about ATDI radio planning and network optimization
More information about ICS designer
About PKP: http://pkp.pl/